2020 Safe Routes to School

  • Project typeSidewalk Improvements
  • Project scheduleConstruction began September 2, 2025
  • Contractor namePalmer Hall Construction
  • Completion DateSeptember 16, 2026

The Safe Route to School Project will improve pedestrian paths in the vicinity of Crow Leadership Academy, Thornton Elementary, and Webb Elementary for students walking to school. The City will be responsible for the design costs and any right-of-way costs. This project is funded by This project is funded by the Transportation Alternatives Set-Aside (TASA) Program through the Texas Department of Transportation (TxDOT).

Project Updates

Project Updates:

Pedestrian improvements serving the Thornton, Webb, and Crow Elementary School areas are substantially complete.

Thornton Elementary School

 Sidewalk improvements along Carter Drive, Sherry Street, Marilyn Lane, Reever Street, and Park Row Drive are substantially complete. A section of newly constructed sidewalk along the east side of Carter Drive, from just south of Rosie Way to Patio Terrace, will be replaced to bring it into compliance.

Webb Elementary School

The pedestrian signal at Cooper Street is complete. Sidewalk improvements along Center Street, between Rogers Street and Slaughter Street, are substantially complete.

Crow Elementary School

Sidewalk improvements along Ruth Street, Sunnyvale Drive, Cardinal Street, Highland Drive, and Raines Street are substantially complete.

Frequently Asked Questions

When is the contractor allowed to work?

The contractor is allowed to work from 7 AM to 6 PM (Central Standard Time) and from 7 AM to 8 PM (Central Daylight Time).

Will I still have water service during construction?

Yes, you will continue to have water service throughout construction. If there is a planned water shut-off, you will be notified at least 48 hours in advance. In the case of an emergency shut-off, water service may be temporarily interrupted for a few hours.

Will construction cause travel delays?

While the construction of the sidewalk is not expected to significantly impact traffic, there may be slight delays during specific phases of the project. We recommend staying alert for any signage and planning your route accordingly to ensure a smooth travel experience.

Will I have access to my driveway?

Driveway access will be available during most of the project. If the contractor must close or remove your driveway, you will be given 48-72 hour notice.

Will my trash be picked up during construction?

Yes. Your neighborhood's regularly scheduled trash and recycling pickup days will continue as normal during construction.