 Truck Loads

The excavation for the future Globe Life Field began on Monday on the eastern part of the project site, which is located in what was formerly the Lot B parking lot.

The excavation is being overseen by Manhattan Construction Company, the general contractor of the project. Crews will work 24 hours a day, six days a week (excluding Sunday) on the excavation with the exception of during major events at AT-T Stadium.

Approximately 1.3 million cubic yards of dirt will be excavated from the site, according to the Texas Rangers. It will take an estimated 97,000 total truck loads to haul the dirt away from the site with the majority being taken to theArlington Landfill.

Substantial completion of the excavation stage is expected by the end of January 2018.

Globe Life Field is a $1.1 billion dollar public-private partnership with the Texas Rangers and City of Arlington. The ballpark will be 1.7 million square feet in size, compared to 1.4 million square feet for the current Globe Life Park, and will be situated on a 13-acre site south of the current facility. Seating capacity is approximately 41,000 for Globe Life Field, which will open in March 2020.

HKS is the design architect for the project.

 Globe Life Field

Related articles:

  • Arlington, Texas Rangers Celebrate Groundbreaking of Future Globe Life Field
  • Latest "Home Plate Update" Features New Texas Rangers Ballpark Renderings
  • Texas Rangers, HKS Release Revised Renderings of Globe Life Field
-*

Major League Baseball trademarks and copyrights are used with permission of MLB Advanced Media, L.P. All rights reserved.

Ballpark Project, Texas Rangers
Business, Economic Development, Headlines, News, Sports