Construction for this project began on April 6th, 2026. The contractors are on a good pace and are roughly on schedule. Currently, the drainage system has been tied into the new outfall and the old one has been abandoned. Crews are now focused on the remaining components such as installing the rest of the improved drainage system and sanitary sewer lines.
A public meeting to learn more about this project was held on Wednesday, March 11, 2026 from 6:00pm to 7:00pm at the Arlington Police Department - West District Center, located at 2060 West Green Oaks Boulevard, Arlington, TX 76013. There was a short presentation followed by a question and answer session.