Brown Boulevard Sidewalk Improvements

  • Project typeSidewalk Improvements
  • Project scheduleConstruction anticipated to begin June 30, 2026
  • Contractor namePeachtree Construction, LTD
  • Completion DateSeptember 30, 2026

This project involves the construction of Americans with Disabilities Act (ADA) compliant sidewalks and pedestrian curb ramps along both sides of Brown Boulevard from North Collins Street to Hidden Ridge Drive. Additionally, the project includes the removal and replacement of an existing drainage box culvert headwall located on the north side of Brown Boulevard between Summer Creek Circle and Summer Creek Lake. These improvements are intended to enhance pedestrian connectivity, safety, and accessibility along the project corridor. The installation of ADA-compliant ramps and continuous sidewalks will improve compliance with federal accessibility standards while supporting the City’s broader pedestrian mobility, and walkability initiatives.

The project also includes asphalt milling and overlaying and miscellaneous concrete repairs on Brown Boulevard. The asphalt milling and overlay process removes two inches of existing asphalt pavement, repairs road base failures, and resurfaces the roadway with a new two-inch asphalt surface course. Miscellaneous concrete repairs include removal and replacement of dilapidated curb and gutter and driveway approaches. 

Funding for this project was included in the voter-approved 2018 Bond Election. Funding sources are the Street Bond Fund and the Street Maintenance Sales Tax Fund. This project aligns with the Council Priorities to Enhance Mobility.

Project Updates

Project Update Coming Soon.


A public meeting to learn more about this project was held on Thursday, April 30, 2026, at 6:00 p.m. in the [re}Brary Room A & B at the George W. Hawkes Downtown Library, located at 100 South Center Street, Arlington, TX 76010. There was a short presentation followed by a question and answer session.

Frequently Asked Questions

Will I have access to my driveway?

Driveway access will be available during most of the project. If your driveway is slated for reconstruction, the contractor will provide you with written notice, so you have time to make other arrangements for vehicle parking.

Will my trash be picked up during construction?

Yes. Your neighborhood's regularly scheduled trash and recycling pickup days will continue as normal during construction.

Will my mail be delivered during construction?

Yes. Your mail and packages will be delivered as normal.

How drivable will my street be during construction?

The contractor will always provide as much access to your street as possible. However, at times it may be necessary to temporarily close a portion of the street during the day. Though access may be limited, if emergencies arise, the contractor will work with you to the best of their abilities to grant you access to your driveway.

Will I still have water service during construction?

Yes. You will continue to have water service during construction. There may be at times, however, that water may be temporarily shut off for a couple of hours during the day. You will be notified of any planned interruptions by the contractor.

Location

Brown Boulevard, Arlington, TX   View Map