Streets Closed Under SH 360 as TxDOT Completes Bridge Work
By Office of Communication
Posted on August 17, 2020, August 17, 2020

I-30 Detour Map

TxDOT is alerting drivers to two street closures under SH 360. The agency says Lamar Boulevard will be closed through 5 a.m., Aug. 19, 2020 under the highway. 

Both directions of Abram Street are also closed under SH 360 through 3 p.m. Aug. 21, 2020 for bridge work. Each closure includes a brief detour.

A complete list of openings and closures is below with new additions in bold.

Click here to learn more about the I-30/SH 360 Interchange Project.

I-30 Mainlanes and Ramps

I-30 Mainlanes

  • Aug. 18 &19, 9 a.m.-3 p.m.: East and westbound I-30 from Baird Farm Road to SH 360 will have the far-left lane closed for construction activities.
  • Aug. 22, 8 a.m.-7 p.m.: The right, outside lane of I-30 westbound mainlines will be closed between Great Southwest Parkway and SH 360 to remove temporary concrete traffic safety barrier and pavement striping to open the new I-30 westbound exit ramp to SH 360/Six Flags Drive.
  • Through summer 2020: The right, outside auxiliary lane between Great Southwest Parkway to 0.2 miles east of Six Flags Drive exit ramp is closed for construction of new westbound exit ramp to Six Flags Drive. 
  • Nightly, Sept. 8-10, 8 p.m.-5 a.m.: I-30 eastbound mainlanes will be reduced to one lane between Six Flags Drive and Ballpark Way for bridge construction. EXPECT DELAYS.

I-30 Eastbound Exit to SH 360 Southbound

  • This direct connector ramp is now in service

I-30 Westbound Exit to AT&T Way/Baird Farm Road

  • Continuously through Aug. 31: The I-30 westbound exit to AT&T Way/Baird Farm Road will be closed for pavement reconstruction in the median. Traffic will be directed to exit Ballpark Way and proceed to the AT&T Way/Baird Farm Road intersection

I-30 Eastbound Entrance from AT&T Way/Baird Farm Road

  • Continuously through Aug. 31: The I-30 eastbound entrance from AT&T Way/Baird Farm Road will be closed for pavement reconstruction in the median. Traffic will be directed to the prior entrance from FM 157/Collins Street.

I-30 Westbound Exit to SH 360/Six Flags Drive

  • Anticipated, Aug. 22: A new I-30 westbound exit ramp to SH 360/Six Flags Drive will be opened to traffic, replacing the existing loop exit ramp. Exiting traffic will pass through a signalized intersection to continue across I-30 towards SH 360. BE AWARE OF NEW TRAFFIC PATTERN.

I-30 Westbound Entrance from SH 360/Six Flags Drive

  • Anticipated, Aug. 22: A new traffic signal will be activated at the intersection with the new, permanent I-30 westbound exit ramp to SH 360/Six Flags Drive. Traffic will pass through this signalized intersection to continue on to access the westbound I-30 entrance ramp. BE AWARE OF NEW TRAFFIC PATTERN.

I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road

I-30 Eastbound Frontage Road between Convention Center Drive and Ballpark Way access ramp

  • Aug. 22, 9 a.m.-7 p.m.: The I-30 eastbound frontage road between Convention Center Drive and the Ballpark Way northbound access ramp will be closed for pavement striping.

I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center Street and Duncan Perry Road

  • Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlanes and Ramps

SH 360 Southbound Mainlanes

  • Aug. 21, 9 a.m.-3 p.m.: The left, inside lane of SH 360 southbound mainlanes will be closed between Division Street and Mitchell Street for bridge work.
  • Continuously through Oct. 31: SH 360 southbound mainlanes will be reduced to two lanes between Avenue J and Six Flags Drive for median utility work. EXPECT DELAYS. 
  • Nightly through Aug. 28, 7 p.m.-6 a.m. (excluding holiday blackouts): SH 360 southbound mainlanes will be reduced to one lane at various locations between Division Street and Kingswood Boulevard to complete pavement work.
  • Daily through Sept. 30, 9 a.m.-3 p.m. (excluding Sundays and holiday blackouts): SH 360 southbound mainlanes will have various lanes closed between Division Street and Kingswood Boulevard to complete various work.

SH 360 Northbound Mainlanes

  • Aug. 22, 6 a.m.-7 p.m.: The left, inside lane of SH 360 northbound mainlanes will be closed between Mitchell Street and Division Street for bridge work.
  • Nightly through Aug. 28, 7 p.m.-6 a.m. (excluding holiday blackouts): SH 360 northbound mainlanes will be reduced to one lane at various locations between Kingswood Boulevard and Division Street to complete pavement repairs.
  • Daily through Sept. 30, 9 a.m.-3 p.m. (excluding Sundays and holiday blackouts): SH 360 northbound mainlanes will have various lanes closed between Kingswood Boulevard and Division Street to complete various work.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard 

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Entrance from Mayfield Drive

  • Aug. 18, 9 a.m.-3 p.m.: The SH 360 southbound entrance from Mayfield Drive will be closed to place traffic safety devices.

    SH 360 Frontage Road

    SH 360 Southbound Frontage Road

    Avenue K to Avenue J

    • Through summer 2020: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.

    SH 360 South-to-North U-turn at Lamar Boulevard

    • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 South-to-North U-turn at Six Flags Drive

    • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 South-to-North U-Turn at Abram Street

    • Continuously through Sept. 30: The SH 360 south-to-north U-turn at Abram Street will be closed for SH 360 bridge work.

    SH 360 Northbound Frontage Road

    Billy B Avenue to Donald Terrace

    • Continuously through Aug. 28: The left, inside lane of SH 360 northbound frontage road between Billy B Avenue and Donald Terrace is closed.

    Randol Mill Road to Avenue E

    • Continuous through Dec. 15: The SH 360 northbound frontage road between Randol Mill Road and Avenue E will be reduced to one lane for underground utility work.

    SH 360 North-to-South U-Turn at Abram Street

    • Continuously through Sept, 30: The SH 360 north-to-south U-turn at Abram Street will be closed for SH 360 bridgework.

    SH 360 North-to-South U-turn at Six Flags Drive

    • The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    SH 360 North-to-South U-turn at Lamar Boulevard

    • The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

    Local Streets

    Lamar Boulevard

    • Daily and nightly, Aug. 13-23, 9 a.m.-3 p.m. and 8 p.m.-5 a.m.: The right, outside lane of westbound Lamar Boulevard under SH 360 will be closed for truck access.
    • Continuously through through Aug. 19, 5 a.m.: Lamar Boulevard under SH 360 will be closed for bridge removal. Eastbound traffic will be detoured south to Six Flags Drive, crossing under SH 360 and returning via the SH 360 northbound frontage road to Lamar Boulevard. Westbound traffic will be detoured north to Avenue J, crossing over SH 360 and returning via the SH 360 southbound frontage road.

    Avenue F

    • Through winter 2020, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

    Copeland Road

    • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
    • PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

    Majesty Drive

    • Continuously through Aug. 28: The SH 360 northbound frontage road intersection with Majesty Drive will be closed for utility work. Traffic will be detoured east on Glenn Drive and north on 106th Street to reach Majesty Drive.

    Glenn Drive

    • Continuously through Aug. 28: The SH 360 northbound frontage road intersection with Glenn Drive will be closed for utility work. Traffic will be detoured east on Randol Mill Road, and north on 106th St to reach Glenn Drive.

    Convention Center Drive/Copeland Road Intersection 

    • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

    105th Street

    • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.

    Abram Street

    • Daily, through Aug. 21, 9 a.m.-3 p.m.: Eastbound and westbound Abram Street lowest level will be closed under SH 360 for bridge work. Eastbound traffic will be detoured south along the frontage road to cross SH 360 at Mitchell Street and return to Abram Street via the northbound frontage road. Westbound traffic will be detoured north along the frontage road to cross SH 360 at Division Street and return to Abram Street via the southbound frontage road.
    Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects
    News, Headlines, Streets