Lane Closures Planned on I-30 as Part of SH 360 Interchange Project
By Office of Communication
Posted on June 11, 2019, June 11, 2019

30-360 project

Editor's note: This article was originally published June 10 and has now been updated to include new closure dates for Mayfield Road and Park Row Drive. 

If you use eastbound Interstate 30, prepare for delays Tuesday night. TxDOT is closing all but one lane between Ballpark Way and SH 360 starting at 8 p.m. The lanes should reopen by 5 o'clock Wednesday morning. Crew will use the time to move concrete safety barriers, as they work to complete the I-30/SH 360 Interchange Project. 

A complete list of closures is below with new and upcoming closures in bold.  

Click here for more on the I-30/SH 360 Project.

I-30 Mainlanes & Ramps

Ballpark Way to SH 360

  • Overnight, June 11, 8 p.m.-5 a.m.: I-30 eastbound mainlanes will be reduced to one lane between Ballpark Way and SH 360 to move temporary concrete traffic safety barrier. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES. 

I-30 Eastbound Entrance from Copeland Road

  • Through fall 2020: A temporary eastbound I-30 entrance ramp will be opened and accessible from Copeland Rd between Ballpark Way and SH 360.

I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road.

I-30 HOV Lanes (Between Great Southwest Parkway & Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2020, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center Street and Duncan Perry Road

  • Through 2020, The eastbound HOV lane access near Center St and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlanes & Ramps

SH 360 Southbound Mainlanes

Brown Boulevard to I-30

  • Overnight, June 10, 8 p.m.-5 a.m.: The right, outside lane of SH 360 southbound mainlanes will be closed between Brown Boulevard and I-30 to place temporary concrete traffic safety barrier. 

Division Street to Mitchell Street

  • June 29, 6:30a.m. - June 30: SH 360 southbound mainlanes will be reduced to one lane between Division Street and Mitchell Street to place Abram Street bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

Mitchell Street to Pioneer Parkway

  • June 16, 6:30 a.m.-Jun 17, 12 a.m.: SH 360 southbound mainlanes will be reduced to one lane between Mitchell Street and Pioneer Parkway to place Park Row Drive bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

Mitchell Stree to Mayfield Road

  • Daily, through June 14, 9 a.m.-3 p.m.: The left, inside lane of SH 360 southbound mainlanes will be closed between Mitchell Street and Mayfield Road for truck access.

Arkansas Lane to I-20

  • June 15, 6:30 a.m. -June 16, 12 a.m.: SH 360 southbound mainlanes will be reduced to one lane between Arkansas Lane and I-20 to place Mayfield Road bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

SH 360 Northbound Mainlanes

I-20 to Mayfield Road

  • June 15, 6:30 a.m.-June 16, 12 a.m.: SH 360 northbound mainlanes will be reduced to one lane between I-20 and Arkansas Lane to place Mayfield Road bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

Mayfield Road to Mitchell Street

  • Daily, through June 14, 9 a.m.-3 p.m.: The left, inside lane of SH 360 southbound mainlanes will be closed between Mayfield Road and Mitchell Street for truck access.

Pioneer Parkway to Mitchell Street

  • June 16, 6:30 a.m.-Jun 17, 12 a.m.: SH 360 northbound mainlanes will be reduced to one lane between Pioneer Parkway and Mitchell Street to place Park Row Drive bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

Mitchell Street to Division Street

  • June 29, 6:30 a.m. -June 30, 12 a.m.: SH 360 northbound mainlanes will be reduced to one lane between Mitchell Street and Division Street to place Abram Street bridge beams. EXPECT SIGNIFICANT DELAY. SEEK ALTERNATE ROUTES.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Entrance from Six Flags Drive

  • PERMANENT: The southbound SH 360 entrance ramp from Six Flags Drive will be closed to place sanitary sewer. Traffic will be directed to the next entrance ramp from Abram Street

SH 360 Southbound Entrance from Arkansas Lane

  • Daily, June 12-14, 9 a.m.-3 p.m.: The SH 360 southbound entrance from Arkansas Lane will be closed to place temporary concrete traffic safety barrier.

SH 360 Frontage Road

SH 360 Southbound Frontage Road

Avenue K to Avenue J

  • Through October 2019: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.

SH 360 South-to-North U-turn at Lamar Boulevard

  • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Six Flags Drive

  • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Park Row Drive

  • Through June 24: The SH 360 south-to-north U-turn at Park Row Drive will be closed for bridge construction.

SH 360 South-to-North U-turn at Mayfield Road

  • Continuously June 14, 7 a.m.-June 22, 5 p.m.: The SH 360 south-to-north U-turn at Mayfield Road will be closed for bridge work.

SH 360 Northbound Frontage Road

SH 360 North-to-South U-turn at Six Flags Drive

  • The SH 360 north-to-south U-turn at Six Flags Dr will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Lamar Blvd

  • The SH 360 north-to-south U-turn at Lamar Blvd will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Park Row Drive

  • Continuously, through June 24: The SH 360 north-to-south U-turn at Park Row Drive will be closed for bridge construction.

SH 360 North-to-South U-turn at Mayfield Rd 

  • Continuously June 14, 7 a.m.-June 22, 5 p.m.: The SH 360 north-to-south U-turn at Mayfield Road will be closed for bridge work.

Local Streets

Ballpark Way

  • Through Winter 2019: The right, outside lane of northbound Ballpark Way between I-30 and Brinker Court will be closed for construction of new westbound frontage road connection.

I-30 entrance from Ballpark Way.

  • PERMANENT: The northbound Ballpark Way ramp to eastbound I-30 will be closed for reconstruction to connect with Copeland Road through winter 2019. Northbound Ballpark Way traffic may exit to Copeland Road, turn right and enter on a temporary eastbound I-30 entrance ramp.

Lamar Boulevard

  • Overnights, June 11-13, 8 p.m.-5 a.m.: Eastbound and westbound Lamar Boulevard between the SH 360 frontage roads will be closed for bridge work. Eastbound traffic will be detoured to Six Flags Drive and return via the SH 360 northbound frontage road. Westbound traffic will be detoured to Avenue J and return via the SH 360 southbound frontage road. 

Avenue G

  • Through Summer 2019, 800 block of Avenue G is limited to westbound traffic movement.

Avenue F

  • Through Summer 2019, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

Copeland Road

  • Continuously, eastbound Copeland Road between Ballpark Way and Six Flags Drive is closed for new pavement and bridge construction.
  • Through winter 2019: Copeland Road access to Six Flags Drive is closed for reconstruction of bridges over Johnson Creek and new pavement to Six Flags Drive. Traffic is forced onto the new temporary eastbound I-30 entrance ramp between Johnson Creek and SH 360.
  • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage road will be closed.
  • PERMANENT: Westbound Copeland Road from Six Flags to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

Abram Street

  • June 29, 6:30 a.m.-June 30, 12 a.m.: Eastbound and westbound Abram Street will be closed between the SH 360 frontage roads to place bridge beams. Eastbound Abram Street will be detoured to Mitchell Street. Westbound Abram Street will be detoured to Division Street.

Park Row Drive

  • June 15, 6:30 a.m.-Midnight: Eastbound and westbound Park Row Drive will be closed between the SH 360 frontage roads to place bridge beams. Eastbound Park Row Drive will be detoured to Pioneer Parkway. Westbound Park Row Drive will be detoured to Mitchell Street.

Mayfield Road

  • June 16, 6:30 a.m.-Midnight: Eastbound and westbound Mayfield Road will be closed to place bridge beams. Westbound traffic will be detoured to cross at Arkansas Lane, and eastbound traffic will be detoured to cross at Cummins Street.

105th Street 

  • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.
Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects
News, Headlines, Streets