No New Lane Closures for I-30/SH 360 During July 4th Weekend
By Office of Communication
Posted on June 28, 2016, June 28, 2016

No New Lane Closures

To help ease Fourth of July weekend traffic congestion, no new short-term lane closures except for emergency closures are scheduled between noon July 1 and noon July 5 as part of the $233 million Interstate 30/SH 360 Interchange Project.

From now until Friday, the southbound outer shoulders of the SH 360 main lanes will be closed between Ave J and Ave K for asbestos abatement.

From now until later this fall, westbound and eastbound Lamar Boulevard/Ave H will be reduced to one lane approaching SH 360 for construction of a new southbound frontage road intersection. All eastbound and westbound Lamar Boulevard traffic crossing under SH 360 will be moved to the south side of the overpass.

From now through summer 2017, eastbound and westbound Ave F traffic will be reduced to one lane each direction and shifted to the south side of Ave F for reconstruction of Ave F.

From now until later this summer, the following roads will be affected:

Avenue F from Avenue E to 111th Street east and westbound traffic will be reduced to one lane each direction and shifted to the south side of Avenue F.

Avenue G, eastbound from Avenue H Eastbound Avenue G from Avenue H will be closed. Traffic will be detoured to 111th Street for business access.

Avenue G, 1700 feet west of 111th Street to 111th Street Eastbound and westbound traffic will be reduced to one lane each direction and shifted to the north side of Avenue G.

Permanent: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way has been permanently closed.

Continuously: Eastbound Copeland Road between Ballpark Way and Six Flags Drive has been reduced to one lane for general construction.

To stay up-to-date on the Interstate 30/SH 360 Interchange Project, visit www.keep30360moving.org.