Plan for minor delays on several roads this week as TxDOT continues work on its I-30/SH 360 project. 

Various lanes will be closed on Abram Street, Park Row Drive and Mayfield Road at SH 360 while crews work. The closures are only scheduled between 9 a.m. and 3 p.m. and will not require detours. 

A complete list of closures is below with new additions in bold.

Click here to learn more about the I-30/SH 360 Interchange Project.

I-30 Mainlanes and Ramps

I-30 Eastbound Entrance from Copeland Road

  • Through fall 2020: A temporary eastbound I-30 entrance ramp will be opened and accessible from Copeland Road between Ballpark Way and SH 360.

I-30 Eastbound Entrance from Convention Center Dr/Copeland Road Intersection 

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road

I-30 HOV Lanes (between Great Southwest Parkway and Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2021, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center St and Duncan Perry Road

  • Through 2021, The eastbound HOV lane access near Center Street and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlaines and Ramps

SH 360 Southbound Mainlanes

  • Daily through Jan. 31, 9 a.m.-3 p.m.: The left, inside lane of SH 360 southbound mainlanes between Division Street and Kingswood Boulevard will be closed for truck access.

SH 360 Northbound Mainlanes

  • Daily through Jan. 31, 9 a.m.-3 p.m.: The left, inside lane of SH 360 northbound mainlanes between Kingswood Boulevard and Division Street will be closed for truck access.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard 

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Frontage Road

SH 360 Southbound Frontage Road

Avenue K to Avenue J

  • Through winter 2020: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.

Bardin Road to Campfire Creek Drive

  • Daily through Jan. 31, 9 a.m.-3 p.m.: The right, outside lane of SH 360 southbound frontage road between Bardin Road and Campfire Creek Drive will be closed for utility work.
  • Continuously through Jan. 31: The right shoulder of SH 360 southbound frontage road between Bardin Road and Campfire Creek Drive will be closed for utility work.

SH 360 South-to-North U-turn at Lamar Boulevard

  • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Six Flags Drive

  • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 Northbound Frontage Road

Glenn Drive to Avenue E

  • Continuously through Feb. 29: The SH 360 northbound frontage road between Glenn Drive and Avenue E will be reduced to one lane for underground utility work.

At Mitchell Street

  • Daily through Jan. 31, 9 a.m.-3 p.m.: The left turn lane of SH 360 northbound frontage road at Mitchell Street will be closed for sound wall construction.

SH 360 North-to-South U-turn at Six Flags Drive

  • The SH 360 north-to-south U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Lamar Boulevard

  • The SH 360 north-to-south U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

Local Streets

I-30 Entrance from Ballpark Way

  • PERMANENT: The northbound Ballpark Way ramp to eastbound I-30 will be closed for reconstruction to connect with Copeland Road. Northbound Ballpark Way traffic may exit to Copeland Road, turn right and enter on a temporary eastbound I-30 entrance ramp.

Avenue G

  • Through winter 2020, 800 block of Avenue G is limited to westbound traffic movement.

Avenue F

  • Through winter 2020, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

Copeland Road

  • Continuously, eastbound Copeland Road between Ballpark Way and Six Flags Drive is closed for new pavement and bridge construction.
  • Through winter 2020: Copeland Road access to Six Flags Drive is closed for reconstruction of bridges over Johnson Creek and new pavement to Six Flags Drive. Traffic is forced onto the new temporary eastbound I-30 entrance ramp between Johnson Creek and SH 360.
  • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage is closed.
  • PERMANENT: Westbound Copeland Road from Six Flags Drive to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

105th Street

  • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.

Abram Street

  • Daily through Jan. 31, 9 a.m.-3 p.m.: Various lanes of eastbound and westbound Abram Street will be closed at SH 360 for bridge work.

Park Row Drive

  • Daily through Feb. 28, 9 a.m.-3 p.m.: Various lanes will be closed on Park Row Drive at SH 360 on an as-needed basis to complete minor work.

Mayfield Road

  • Daily through Feb. 28, 9 a.m.-3 p.m.: Various lanes will be closed on Mayfield Road at SH 360 on an as-needed basis to complete minor work.
Enhance Regional Mobility, I-30/SH 360 Interchange, SH 360 Widening Project, Street Construction Projects