Lane Closures Planned in Both Directions of I-30 This Week
By Office of Communication
Posted on August 28, 2019, August 28, 2019

30-360 project

Editor's Note: TxDOT issued updated closures Wednesday, August 28.

Expect major delays on Interstate 30 this week while crews install bridge beams. Tuesday, Aug. 27, westbound I-30 will be reduced to one lane between Great Southwest Parkway and Ballpark Way starting at 8 p.m. The interstate should fully reopen before Wednesday morning rush hour. 

Then, the closures move the other direction.

Wednesday, Aug. 28, eastbound I-30 will be reduced to one lane between Ballpark Way and SH 360 starting at 8 p.m. The lanes will reopen for Thursday morning rush hour. 

The work is part of the I-30/SH 360 Project. Click here for more information. 

A complete list of closures is below with new and upcoming closures in bold.  

I-30 Mainlanes & Ramps

Ballpark Way to SH 360

  • Overnight, Aug. 28, 8 p.m. - 5 a.m.: Eastbound I-30 mainlanes will be reduced to one lane between Ballpark Way and SH 360 for bridge beam placement. EXPECT DELAYS. SEEK ALTERNATE ROUTES.

Ballpark Way to Six Flags Drive

  • Aug. 29, 9 a.m.-3 p.m.: The left, inside lane for eastbound I-30 mainlanes between Ballpark Way and Six Flags Drive will be closed to move temporary, concrete traffic safety barrier.

I-30 Eastbound Entrance from Baird Farm Road

  • Overnight, Aug. 28, 8 p.m.-5 a.m.: The I-30 eastbound entrance from Baird Farm Road will be closed for bridge work. Traffic will be directed to enter I-30 from Collins Street.
  • Aug. 29, 9 a.m.- 3 p.m.: The I-30 eastbound entrance from Baird Farm Road will be closed to move temporary, concrete traffic safety barrier. Traffic will be directed to enter I-30 from Collins Street.

I-30 Eastbound Entrance from Copeland Road

  • Overnight, Aug. 28, 8 p.m.- 5 a.m.: The I-30 eastbound entrance from Copeland Road will be closed for bridge work. Traffic will be directed to enter I-30 from Nolan Ryan Expressway

I-30 Eastbound Entrance from Convention Center Drive/Copeland Road Intersection

  • PERMANENT: The eastbound I-30 entrance ramp available from the Convention Center Drive/Copeland Road intersection will be closed permanently. Traffic will continue to have access to the ramp to northbound Ballpark Way.

I-30 Eastbound Entrance from Northbound Ballpark Way

  • PERMANENT: The eastbound I-30 entrance ramp from northbound Ballpark Way will be closed permanently for the construction of a new northbound Ballpark Way connector to eastbound Copeland Road.

I-30 Westbound Mainlanes

  • Overnight, August 28, 8 p.m.- 5 a.m.: Westbound I-30 mainlanes will be reduced to one lane between Great Southwest Parkway and Ballpark Way for bridge beam placement. EXPECT DELAYS. SEEK ALTERNATE ROUTES.

I-30 Westbound Entrance from Six Flags Drive/SH 360 

  • Aug. 27, 8 p.m.- 5 a.m.: The I-30 westbound entrance from Six Flags Drive/SH 360 will be closed for bridge work. Traffic will be directed to eastbound on I-30 to exit SH 161. Traffic will follow the detour to U-turn and return via westbound I-30.

I-30 HOV Lanes (Between Great Southwest Parkway & Cooper Street)

Westbound I-30 HOV lane west of SH 161

  • Through 2020, The westbound HOV lane west of SH 161 will be closed. TEXpress lane traffic will be directed into the I-30 westbound general main lanes west of SH 161.

Eastbound I-30 HOV lane between Center Street and Duncan Perry Road

  • Through 2020, The eastbound HOV lane access near Center St and lane through Tarrant County will be closed. TEXpress lane traffic will enter at SH 161.

SH 360 Mainlanes & Ramps

SH 360 Southbound Mainlaines 

Division Street to Kingswood Boulevard

  • Daily, through August 31, 9 a.m.-3 p.m.: Various lane closures on SH 360 southbound mainlanes to repair safety devices.

SH 360 Northbound Mainlanes 

Kingswood Boulevard to Division Street

  • Daily, through August 31, 9 a.m.-3 p.m.: Various lane closures on SH 360 northbound mainlanes to repair safety devices.  

Green Oaks Boulevard/Kingswood Boulevard to Mayfield Road

  • Nightly, through August 28, 7 p.m.-6 a.m.: The left, inside lane of northbound SH 360 mainlanes between Green Oaks/Kingswood Boulevards and Mayfield Road will be closed for pavement work.

SH 360 Southbound Entrance from Brown Boulevard/Avenue K

  • PERMANENT: The SH 360 southbound entrance from Brown Boulevard/Avenue K is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Exit to Lamar Boulevard

  • PERMANENT: The SH 360 southbound exit to Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured to exit to Brown Boulevard/Avenue K and follow the SH 360 southbound frontage road to Lamar Boulevard. A new exit ramp will be constructed to Avenue J/Lamar Boulevard/Six Flags Drive.

SH 360 Southbound Entrance from Lamar Boulevard

  • PERMANENT: The SH 360 southbound entrance from Lamar Boulevard is PERMANENTLY CLOSED. Traffic is detoured along the SH 360 southbound frontage road to enter from the Six Flags Drive entrance ramp. A new entrance ramp will be constructed between Lamar Boulevard and Six Flags Drive.

SH 360 Southbound Entrance from Six Flags Drive

  • PERMANENT: The southbound SH 360 entrance ramp from Six Flags Drive will be closed to place sanitary sewer. Traffic will be directed to the next entrance ramp from Abram Street

SH 360 Frontage Road

SH 360 Southbound Frontage Road

Avenue K to Avenue J

  • Through October 2019: The SH 360 southbound frontage road is reduced to one lane between Avenue K and Avenue J for construction of new frontage road.

Arkansas Lane to Mayfield Road

  • Continuous, through September 13: The left, inside lane of SH 360 southbound frontage road will be closed between Arkansas Lane and Mayfield Road for sound wall construction.

SH 360 South-to-North U-turn at Lamar Boulevard

  • The SH 360 south-to-north U-turn at Lamar Boulevard will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 South-to-North U-turn at Six Flags Drive

  • The SH 360 south-to-north U-turn at Six Flags Drive will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 Northbound Frontage Road

SH 360 North-to-South U-turn at Six Flags Drive

  • The SH 360 north-to-south U-turn at Six Flags Dr will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Lamar Blvd

  • The SH 360 north-to-south U-turn at Lamar Blvd will be closed while the SH 360 mainlanes and northbound frontage road are under construction.

SH 360 North-to-South U-turn at Mayfield Road

  • Continuously, August 21-23: The SH 360 north-to-south U-turn at Mayfield Road will be closed for bridge work.

Local Streets

Ballpark Way

  • Through Winter 2019: The right, outside lane of northbound Ballpark Way between I-30 and Brinker Court will be closed for construction of new westbound frontage road connection.

I-30 entrance from Ballpark Way.

  • PERMANENT: The northbound Ballpark Way ramp to eastbound I-30 will be closed for reconstruction to connect with Copeland Road through winter 2019. Northbound Ballpark Way traffic may exit to Copeland Road, turn right and enter on a temporary eastbound I-30 entrance ramp.

Avenue G

  • Through Summer 2019, 800 block of Avenue G is limited to westbound traffic movement.

Avenue F

  • Through Summer 2019, eastbound and westbound Avenue F traffic will be reduced to one lane each direction and shifted to the south side of Avenue F for the reconstruction of Avenue F.

Copeland Road

  • Continuously, eastbound Copeland Road between Ballpark Way and Six Flags Drive is closed for new pavement and bridge construction.
  • Through winter 2019: Copeland Road access to Six Flags Drive is closed for reconstruction of bridges over Johnson Creek and new pavement to Six Flags Drive. Traffic is forced onto the new temporary eastbound I-30 entrance ramp between Johnson Creek and SH 360.
  • PERMANENT: Copeland Road between Six Flags Drive and the SH 360 southbound frontage road will be closed.
  • PERMANENT: Westbound Copeland Road from Six Flags to just east of Ballpark Way is permanently closed. Only eastbound Copeland Road traffic will be allowed between Ballpark Way and Six Flags Drive.

Convention Center Drive/Copeland Road Intersection 

  • PERMANENT: The I-30 eastbound entrance ramp available from this intersection was removed permanently from service. Access to northbound Ballpark Way is maintained.

Park Row Drive

  • Daily, Aug. 26-29, 9 a.m. - 3 p.m.: Eastbound and westbound Park Row Drive will be closed under SH 360 for bridge work. Eastbound traffic will be detoured on the SH 360 southbound frontage road to Pioneer Parkway, crossing SH 360 and returning on the SH 360 northbound frontage road. Westbound traffic will be detoured on the SH 360 northbound frontage road, crossing at Mitchell Street and returning on the SH 360 southbound frontage road.

105th Street 

  • PERMANENT: 105th Street between Six Flags Drive and Avenue E is permanently closed and will be removed.

Fielder Road

  • Nightly, August 12-22, 9 p.m.- 5 a.m.: Fielder Road crossing I-30 will be closed for bridge repairs. Traffic will be detoured east and west on I-30 to the next available exit to return to Fielder Road via I-30.