Pre-Application
Conference
The developer or
engineer for sites one acre or larger must attend a pre-application
conference with Environmental Services prior to submitting the
development.
Conferences are
scheduled in 30 minute increments each Tuesday morning in the
Department of Public Works' second floor conference room from 9AM to
noon.
To schedule a
conference, send your preferred date and time to envpreplat@ci.arlington.tx.us.
Suggested items to
bring to the pre-application conference are:
Storm Water
Management Site Plan
Development submittals
of projects for sites 12,000 square feet or larger must include a
preliminary Storm Water Management Site Plan.
A site plan will be
accepted in lieu of a preliminary SWMSP if the site plan shows
development will create less than 5,000 square feet of impervious
surface.
See Article V of the Subdivision
Regulations and the Design
Criteria Manual (pdf) for specific requirements.
[